build basement BS8102

Slab edge formwork.

Slab edge formwork is usually supported off the sides of the excavation.

But sometimes I'm able to do it a bit more easily, cutting less timber.

I like to set out and bang in wooden pegs before I blind with concrete. Get the blinding concrete all round all the pegs. Fix a scaffold board to the pegs so the top of the board is top of concrete. The gaps can have some mud behind that stops the flow of concrete underneath.

build basement BS8102

Use 2x2 not 4x2 because you will need to snap the pegs to get the boards out.

 
  build basement BS8102

build basement BS8102


These examples would be more usual.

build basement BS8102


This is so neatly done they used expanding foam to prevent concrete leaking out.

build basement BS8102


It is important that the waterproof concrete does not lose much grout through narrow gaps because to be waterproof it needs enough cement to fill all the spaces between all the grains of sand.





Back to the Basement Building Questions Answered menu.

build basement BS8102


Back to the Basement Building Construction Manual menu.

build basement BS8102


For a fixed fee of £199 I will answer all your questions by email. More details here.

build basement BS8102


Back one page Forward to next page Forward two pages

Concrete blinding


My training


My supervision